Design, build, manage contractor
In a typical design and build (D&B) procurement, the main contractor is appointed to design and construct the works (as opposed to a traditional contract, where the client appoints consultants to design the development and then a contractor is appointed to construct the works).
In a design, build and manage contract (DBM), the contractor – in addition to shouldering the risks of design and construction – also manages the construction process, sometimes providing operational services over and above building maintenance, such as supplying operational staff and cleaning.
The DBM may also appoint (and contracting with) different works contractors to see the completion of various parts of the project. The contractor therefore is also a project manager.
The client (or their representative) will generally appoint the DBM contractor early-on in the design process so that their experience can be used to improve the cost and buildability of proposals as they develop, as well as to advise on packaging and the risks of interfaces.
[edit] Related articles on Designing Buildings Wiki
- Approved contractor.
- CIS contractors and CIS sub-contractors.
- Commercial manager.
- Construction contract.
- Construction manager.
- Contractor's working schedule.
- Design and manage procurement route.
- Due diligence when selecting contractors or subcontractors.
- Management contractor.
- Principal contractor.
- Procurement route.
- Work package contractor.
- Works contractor.
Featured articles and news
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.